Developing a strategic plan for Avondale School District helps to identify the direction of the District within the framework of our mission and vision. It also outlines the goals, strategies, and actions to ensure the plan is implemented. Every year we actively work to implement the strategic plan in the classroom, around our buildings, and throughout the district. Explore the Avondale 2020 Strategic Plan & Progress updates below to view some of the ways we are taking action!
-
Avondale 2020 Strategic Plan & Progress
Avondale 2020 In Action Avondale 2020 Strategic Plan Avondale 2020 Action Plan Priorities Planning Sessions Resources & Materials 2016-17 Midyear 2020 Plan Progress 2016-17 Year-End 2020 Plan Progress 2017-18 1st Quarter 2020 Plan Progress 2017-18 Year Two Progress 2017-18 Priority Goals Update 2017-18 Strategic Planning Year 2 Mid-Year Summary 2018-19 Priority Goals Update 2018-19 Strategic Planning Year 3 Year Progress Summary February 2018 Update & Forum January 2020 Strategic Planning Mid-Year Sumary
2021 Bond Project Progress
Work to Begin on Avondale High School Parking Lot and Grounds
In the Summer of 2021, the Avondale High School parking lot and main entrance will be renovated to address building safety concerns as well as concerns about the flow of buses, cars and pedestrians in the current design of the parking lot. The renovations are made possible through funds generated by the passage of a $30.7 million bond proposal in November, 2017.
Highlights of the parking lot renovations include:
- Relocation of the current “bus loop” to the back of the building utilizing the staff parking lot.
- Reconfiguration of the current “bus loop” to accommodate school-day visitor parking and parent drop-off and pick-up.
- Designation of the main parking lot as student parking during school days/hours.
- Management of pedestrian traffic into the school building (2021-22 school year).
- During the school day at arrival and dismissal, students who park in the student parking lot or who arrive or depart school via parent or guardian transport, will use the current student entrances / exits in the Field House Lobby.
- All other times during the school day, students and visitors will use a newly constructed safe and secure entryway (once complete).
- Expanded and enhanced student gathering areas and outside classroom space between the planned parent drop-off / pick-up area and the building. Sidewalks, short-wall seating, and landscaping adds inviting accents and functionality.
- Complete re-build of the paved areas rather than re-surfacing to support longer life of the parking lots and sidewalks.
Have questions about this information?
Avondale School District Bond Project Schedule, Progress & Completed Projects
On November 7, 2017, the Avondale School District Community approved a $30.7 million bond proposal that made it possible for the District to move forward with necessary infrastructure upgrades. These upgrades include enhancements to safety, security, and technology; as well as building operation upgrades, such as boiler and lighting replacements, that are designed to save the District money and provide return on investment. Technological advancements in areas like lighting, cooling, and heating have resulted in more energy-efficient equipment. Moving to upgrade to the more cost-effective equipment ensures that necessary improvements are made without impacting the operating budget that supports our classrooms.
-
Avondale High School
Freight Elevator Addition Completed Auditorium Sound Board Completed Interior Renovations: - Serving Line Upgrades
- Orchestra Pit
- Field House Locker Room Renovations
- Field House Mechanical Improvements
- Corridor / Field House / Pool Lighting Improvements
- Pool Equipment Improvements
June 2019 - August 2019
On schedule (bids awarded, contractors selected, completed by Labor Day)LMC / Collaboration Space Renovations May 2019 - August 2019
On schedule (bids awarded, contractors selected, completed by Labor Day)Interior Renovations - Secured Vestibule
- Scene Shop Equipment / Curtain Legs
- Carpe Replacement
- Mechanical Improvements
- AHS Building Lighting Improvements
- Technology Improvements
June 2021 - August 2021 Site / Parking Lot Improvements June 2021 - August 2021 Interior Renovations: - Carpet Replacement
June 2022 - August 2022 -
Avondale Middle School
Bolier Replacement Completed Track Replacement June 2019 - August 2019
On schedule (project began on June 3, 2019)Interior Renovations: - Secured Vestibule
- LMC / Collaboration Space Renovations
- Technology Improvements
- Mechanical Improvements
- Carpet Replacement
- Lighting Improvements
- Locker Room Renovations
June 2021 - August 2021 Interior Renovations: - Carpet Replacement
June 2022 - August 2022 -
Auburn Elementary
Renovations: - Secured Vestibule
- Office Renovations
- Carpet Replacement
- Mechanical Improvements
- Lighting Improvments
June 2020 - August 2020 Playground Equipment Replacement June 2021 - August 2021 Renovations: - Carpet Replacement
June 2022 - August 2022 -
Deerfield Elementary
Renovations: - Secured Vestibule
- Restroom Remodel
- Carpet Replacement
- Mechanical / Lighting Improvements
June 2020 - August 2020 Playground Equipment Replacement June 2021 - August 2021 Renovations: - Carpet Replacement
June 2022 - August 2022 -
R. Grant Graham Elementary
Renovations: - Secured Vesibule
June 2019 - August 2019
On schedule (bids awarded, contractors selected, completed by Labor Day)Renovations - Carpet Replacement
- Mechanical / Lighting Improvements
June 2020 - August 2020 Playground Equipment Replacement June 2021 - August 2021 Renovations: - Carpet Replacement
June 2022 - August 2022 -
Woodland Elementary
Renovations: - Secured Vestibule
- Carpet Replacement
- Mechanical / Lighting Imrovements
June 2020 - August 2020 Playground Equipment Replacement June 2021 - August 2021 Renovations: - Carpet Replacement
June 2022 - August 2022 -
Meadows Learning Center
Renovations: - Separation Walls for GT Program
June 2019 - August 2019
On schedule (bids awarded, contractors selected, completed by Labor Day)Site Improvements: - Reconfigure South Parking Lot
- Parking Lot Replacement
- Playground Equipment Replacement
June 2019 - August 2019
On schedule (bids awarded, contractors selected, completed by Labor Day)Renovations: - Secured Vestibule
- Carpet Replacement
- Mechanical / Lighting Improvements
June 2020 - August 2020 Renovations: - LMC Renovations
June 2021 - August 2021 Renovations: - Carpet Replacement
June 2022 - August 2022 -
Transportation
Transportation Office Addition / Garage Renovation October 2018 - June 2019
On schedule (bids awarded, contractors selected, completed by Labor Day)Site Improvements June 2019 - August 2019
On schedule (bids awarded, contractors selected, completed by Labor Day